Recent Projects
Project Duration 2 days
Capacity 3 Kw
Completion
Assignment
Location Virugambakkam, Chennai, Tamil Nadu


    Jose & Dos Surgical:

    We have done a 3kw off grid Solar Power Plant addition to an existing 1.5kw. The company needed additional power for there extending manufacture hub due to frequent power cut & non maintenance of the existing Solar Power Plant the industry felt difficult in production in this point where the industry came to Glory Power Solutions as there power solution provider. we gave a solution of fixing the existing power plant and add another 3kw to the existing system to give a fix on minimum budget.

    Following Systems where connected to the output:

    1) Tailoring Machine consuming 350 w - 18 numbers

    2) Fan - 3 numbers

    3) Light - 3 numbers